Unless stated, all material © Stover Canal Trust 2023
Charity Number, 1138316 Company Number: 5835573
Restoration of the Ventiford Basin
Ventiford
Basin
is
the
Northern
terminus
of
the
canal.
Clay
from
the
local
area
was
brought
here
overland,
loaded
onto
barges
and
sailed
down
the
canal
to
the
Jetty
Marsh
sea
lock.
Depending
on
the
state
of
the
tide,
barges
would
then
travel
along
the
Whitelake
Channel,
past
Town
Quay
in
Newton
Abbot
and
down
the
River
Teign
to
be
trans-shipped
to
larger
vessels
at
the
docks in Teignmouth.
In
1820,
James
Templer
II’s
son
George
brought
his
Granite
Tramway
here
from
his
quarries
at
Haytor
to
enable
Dartmoor
granite
to
follow
the
same
route
as
the
clay
to
Teignmouth.
This
Dartmoor
granite
was
used
in
the
construction
of
many
prominent buildings in London.
Following
the
opening
of
the
Moretonhampstead
and
South
Devon
Railway
in
1866,
canal
traffic
gradually
declined
and
the
Basin
subsequently
became
redundant
and
steadily
fell
into
disrepair.
Flooding
by
the
adjacent
River
Teign
over
the
decades
left layers of silt which gradually built up and buried all evidence of the canal and tramway.
For
two
weeks
in
2014,
the
excavation
started
of
an
old
barge
which
had
been
laid-up
in
the
basin
when
the
basin
became
redundant
in
the
late
1800’s.
Granite
walls
to
the
basin
were
also
uncovered.
Later
that
year,
whilst
work
was
being
carried
out
by
Devon
County
Council
on
the
construction
of
the
Stover
Trail
cycle
and
walkway,
evidence
of
the
Granite
Trameway
was
uncovered.
A
further
two
week
excavation
continued
in
2015.
It
was
becoming
evident
that
the
open
grassed
area
that
was ‘Ventiford’ held many surprises in store.
Restoration
work
was
greatly
helped
in
the
early
Summer
of
2016
by
the
involvement
of
the
management
and
some
of
the
staff
of
the
local
clay
company,
Sibelco.
Hundreds
of
tonnes
of
silt
were
removed
from
the
canal
channel
and
more
hulked
barges
and granite ‘rails’ were found.
Volunteers
from
the
Waterways
Recovery
Group
later
spent
two
weeks
helping
with
the
work.
They
are
all
members
of
the
Inland Waterways Association and give of their free time to restore old canals all over the country.
The Waterway Recovery Group attracts a wide range of people, from young volunteers taking part in the Duke of
Edinburgh’s Award Scheme; to waterway enthusiasts who wish to make a contribution to restoring and preserving the
system; to people who just want to get outdoors, have fun and learn new skills. www.waterways.org.uk/wrg/
Our thanks go to all the people and organisations that have made the restoration possible.
Here
we
see
Ventiford
picnic
area,
looking
towards
Newton
Abbot
and
before
restoration
started.
The
first
barge
to
be
investigated
was
situated
just
beyond
the
bonfire.
Some
evidence
of
the
canal
basin
granite
walls
can
be
seen.
In
the
distance
alongside
the
Stover
Trail,
is
the
first
short
length
of
the
Granite
Tramway
to
be
uncovered.
May 2014 Excavation of the quay wall
Left picture
Discovery of the granite
tramway November 2014
Right picture
Further length uncovered
May 2015
Further excavation of the first barge took place in
2016. It was fully documented and photographed
prior to being lifted out of the basin.
Sadly the wooden structure quickly began to
deteriorate on exposure to the atmosphere and
just a few small pieces were saved. However,
we have enough detail should someone wish to
build a replica!
In the Summer of 2016 some serious action
took place….
…and two more barges were found
Barge Two
Barge Three
Members of the Waterways Recovery Group made good progress with grouting the walls.
Before the help from the Sibelco team…. and after.
The line of the Granite Tramway can
clearly be seen alongside the Basin.
Careful work by the volunteers from
Sibelco exposed more of the ‘rails’ to
the North.
Crossovers on the Granite Tramway looking South from the Basin.
Built by our forefathers, preserved for our grandchildren
The dam has been constructed and
the basin lined with puddling clay
Whilst levelling the picnic area an area of original working surface was revealed.
The basin started filling with water in Autumn 2019
A replica Crane on the quayside was unveiled in September 2021
The basin was lined with clay.